CloudNala Insights · The Commercial Architecture of Delivery

Commercial Architecture Canvas

One canvas per commitment. Complete it before a price, contract or budget is signed, and revisit it at every re-baseline. Section 0 is the canvas itself: fourteen fields that decide whether price, scope, risk, authority and delivery shape fit together. Sections 1 to 8 are the decision tools from the eight parts of the series. A field is complete only when it points to evidence a reviewer can open.

All example entries (in italics) are illustrative and use abstract units. They are not rates, prices, margins or thresholds, and they are not benchmarks. Replace them with your own.

0The canvas

OutcomeWhat must be true when the work is done, in terms a user would recognise.
Included scopeThe scope inventory version, including production layers.
Excluded scopeEach exclusion with its written consequence.
AcceptanceWho accepts, against which test, within what time.
Party controlling each decisionFrom the Accountability-Control Matrix (section 3).
Client-supplied rolesNamed roles, availability and start dates.
Third partiesEach dependency and the party that manages it.
Infrastructure ownershipWho owns subscriptions, configuration and the bill.
Delivery modelFixed price, phased, capped time and materials, fixed team, outcome milestone or conditional options.
Support and warrantyHypercare, warranty and support, each bounded (section 7).
AssumptionsThe five to ten that move the estimate most.
Change mechanismHow change is raised, estimated, approved and priced.
Re-baseline triggerThe agreed events that reopen scope, effort, duration or price (section 8).
Price basisEffort, gross-up, contingency for named risks and margin as separate lines; run cost as cost per accepted outcome where AI is involved.

1Estimate Evidence Card

Travels with every estimate above an agreed size. Part 1: Precision is not evidence.

Estimate Evidence Card
FieldEntry
Scope source and exclusions
Method (comparable, bottom-up, parametric, expert, model-assisted)
Comparable work and how it differs
Key assumptions
Dependencies and exclusions
Range and confidence (low, likely, high, with drivers)Example: 85 to 140 units, likely 105; medium confidence
Contingency for named risks, shown separately
Reviewer (did not build the estimate)
Change from last version, and why
Re-baseline point

2Effort-Duration Reconciliation

Complete before a date is committed, and whenever a date is imposed. Part 2: Estimate effort before you force duration.

Six steps
StepOutput
1. Effort, independent of date (range)
2. Real capacity (named roles, availability, start)
3. Dependencies, lead times and blocked windows
4. Derived duration range
5. Gap to the desired date, in weeks
6. Lever chosen (scope, phase, capacity, named risk, date) and owner
Lowering the effort figure until it fits the date is not a lever. It hides the gap.

3Accountability-Control Matrix

Every committed outcome mapped to the party that controls each decision and input it needs. Part 3: Fixed price, undefined scope and shared control.

Accountability-Control Matrix
Committed outcomeDecision or input requiredWho controls itWho carries the outcomeAligned?Treatment
Service live by agreed dateProduction environment by week 6Buyer platform teamSupplierNoDates move day for day; standby cost agreed

Treatments for a misaligned row: move the control, move the outcome, define what happens when the controlling party does not deliver, or price the risk as named contingency.

4Requested vs Production Scope Map

Each cell: Supplier, Client, Third party, Excluded (with consequence) or Unknown. No Unknown at commitment. Part 4: The hidden half of the build.

Scope map
Requested capabilityIdentity and securityData and migrationIntegration hardeningNon-functional testingReleaseOperationsSupport and adoptionAI evaluation
Security, backup and recovery, migration reconciliation and basic AI evaluation are never offered as optional extras.

5Solution-to-Option Canvas

Every option is the same defined solution with stated differences. Part 5: Options must come from a defined solution.

Options
FieldOption 1Option 2Option 3
Outcome
Scope included
Scope excluded
Acceptance
Duration range
Delivery model
Risk holder
Key assumptions
Effort, gross-up and contingency (separate lines)
What you give up

Keep four terms apart: cost (what delivery takes), price (what the buyer pays), value (what the buyer gains) and affordability (whether the buyer can pay, in the right budget, at the right time).

6Architecture-Funding Fit Matrix

Technical fit and funding eligibility are separate constraints. Part 6: Your best architecture may break the funding model.

Funding fit
FieldDesign ADesign BDesign C
Technical fit
Run-cost profile (fixed, variable, capped)
Funding line it needs
Funding line available
Period fit
Currency exposure
Run cost per accepted outcome (range, ceiling)
Gap and what would close it
Verdict

Budget, accounting and procurement rules differ between organisations. Complete this section with your finance function.

7Delivery Boundary Schedule

One row per edge. Part 7: Price the boundary, not only the build.

Boundaries
BoundaryWhat crosses itOwner beforeOwner afterService levelCommercial treatmentEnds or reviewed
Go-live to hypercare
Hypercare to warranty
Warranty to support
Production release
Cloud subscription and consumption
AI model change
Third-party services
Exit

8Re-Baseline Trigger Card

Agreed by both parties at signature. Reaching a trigger creates an obligation to re-plan. Part 8: Re-baseline before the variance becomes a surprise.

Triggers
TriggerAgreed thresholdChecked atWho raises itRequired response
Key assumption fails
Effort variance on a work packageExample: more than 15% above plan for work completed
Scope inventory growth
Dependency delay
Contingency drawn faster than progress
Accepted outcomes behind plan
AI cost per accepted outcome above range
Key role vacant

At every checkpoint compare four things against the last baseline: assumptions, scope, effort for work completed, and evidence of accepted outcomes. Then decide: continue, re-baseline (unknown or shared cause), change request (buyer-driven) or recovery plan (supplier-driven).

Buyer sign-offName, role and date
Supplier sign-offName, role and date
Next checkpointDate